During project implementation, the project manager discovers that a team member has usedopen source software. This is a violation of company regulations and will seriously affect theproject’s release.What should the project manager do?
A. Execute the risk management plan.
B. Remove the team member.
C. Log the risk in the risk register.
D. Submit a change request to delete the open source software.

项目经理在项目执行过程中发现团队成员违规使用开源软件,违反公司规章并且将严重影响项目的发布。这时候项目经理应该如何处理?
A.执行风险管理计划。
B.开除该成员。
C.在风险登记册中记录该风险。
D.提交变更请求,删除使用的开源软件。

【解析:纠正措施属于变更,需要提交变更请求。】