PMP:每日一题-4

2019.7.15每日一题: 答案 C

You are a project manager of a company and your project is currently in execution phase.The customer has requested you for additional work. This work will affect the budget, but not the schedule of the project. What should you do next?
A. Add the additional requirements to the project plan.
B. Ignore the request.
C. Explain the change procedure and ask to submit a request for change.
D. Discuss with the project team about the change.

你是公司的项目经理,你的项目目前处于执行阶段。客户已要求你进行其他工作。这项工作将影响预算,但不会影响项目的进度。接下来你应该做什么?
A.将额外要求添加到项目计划中。
B.忽略请求。
C.解释变更程序并要求提交变更请求。
D.与项目团队讨论变更。

【解析:客户提出的其他工作会影响预算,虽然不会影响进度,也要通过变更流程来采取对应措施,因此解释变更程序并要求提交变更请求是最佳选择。】