PMP:每日一题-7

2019.7.18每日一题:

Four months after the approval of the project scope, the client requests features that willgenerate changes to the project management plan, what should the project manager do next?
A. Work on the customer’s request after completion of the project.
B. Proceed with changes if contingency is available.
C. Process a change request.
D. Consult the risk register to identify a solution.

在项目范围获批四个月后,客户请求增加功能,但该请求将可能对项目管理计划产生变更。项目经理下一步应该怎么做?
A.在项目完工之后处理客户的请求。
B.如有应急计划,则进行变更。
C.处理变更请求
D.查阅风险登记册,确定解决方案。

答案:C
解析:对于客户提出的变更,按照变更管理要求进行处理。