2019.7.23每日一题:

At the last minute, a project team implements a new feature that is not included in the scopestatement. To obtain customer approval, what process should the project manager implementnext?
A. Plan Scope Management
B. Validate Scope
C. Perform Integrated Change Control
D. Perform Qualitative Risk Analysis

在最后一刻,项目团队实施了范围说明书中未包含的新功能。若要获得客户的批准,项目经理下一步应执行哪个过程?
A. 制定范围管理计划
B. 核实范围
C. 执行整体变更控制
D. 执行定性风险分析

答案:C
解析:得到客户的批准,正确的做法就是通过整体变更控制,也是四个选项中最好的参考答案。