PMP:每日一题-12

2019.7.25每日一题:

Midway through a project with a 12-month contract, written notice is unexpectedly received from the customer requesting transfer of the project to a competitor, what should the project manager do?

A. Ask company management for assistance.
B. Initiate project closure.
C. Review the project charter.
D. Review the terms of the signed customer contract.

A公司承接了一个为期 12个月的合同。当项目进行到一半的时候,突然接到客户的书面通知将项目转移给竞争公司B。这个时候A公司的项目经理下一步应该做什么?

A. 请求公司管理层的协助。
B. 启动项目收尾工作。
C. 查看项目章程中的相关规定。
D. 查看与客户签署的合同条款。

答案:D
解析:在请示管理层的协助,启动收尾之前,需要查阅合同中的相关规定。