PMP:每日一题-13

2019.7.26每日一题:

A project is near closure, and the developer has finished product development. The projectsponsor now wants the project manager to deliver the product ahead of schedule. What shouldthe project manager do?
A. Ask the sponsor to withdraw the request.
B. Hold a stakeholder meeting.
C. Deliver the product as originally scheduled.
D. Have the developer start project wrap-up activities, and prepare to deliver ahead ofschedule.

项目接近尾声,开发人员也已完成了产品的开发。项目发起人要求项目经理提前向客户交付该产品。项目经理应该怎么做?
A.找项目发起人谈话试图说服他收回请求。
B.召开干系人会议。
C.仍按原计划发布产品。
D.让开发人员展开项目的收尾工作,准备提前交付。

答案:D
解析:项目已经完成项目产品需求,可以进行提前收尾,PMI关于项目收尾的管理要求。