2019.7.29每日一题:

A new warehouse is ready for operations. Before operations begin, the project manager mustprepare the final project report. What should the project manager refer to?
A. Lessons learned, project charter, and work breakdown structure (WBS)
B. Project baselines,accepted deliverables, and earned value (EV)
C. Checklists, responsibility assignment matrix(RAM), and risk management plan
D. Accepted deliverables, lessons learned, and transition criteria

一个新的仓库准备好运营。运营开始之前,项目经理必须准备最终项目报告。项目经理应该查阅哪些文件?
A.经验教训、项目章程和工作分解结构(WBS)
B.项目基准、已验收的可交付成果和挣值(EV)
C.核对表、责任分配矩阵(RAM)和风险管理计划
D.已验收的可交付成果、经验教训和移交标准

答案:D
解析:四个参考答案中,作为项目转入运营之前的最终报告,最好的内容是参考答案D。