You are the project manager for a Project. You are updating the WBS during Define Activities, which is often called __?
A. Refinements
B. Updates
C. Activities
D. Supporting detail

你是项目的项目经理。你是在定义活动期间更新WBS,通常称为____?
A.渐进明细
B.更新
C.活动
D.支持细节

参考答案:A
解析:在定义活动期间更新WBS通常称为渐进明细。它一般发生在风险较高的项目中。参考PMBOK185。