PMP:每日一题-30

2019.8.20每日一题:

A company’s director is concerned with project failure and hires a project manager todetermine where additional funding should be allocated to ensure success. For what activityshould the project manager recommend additional funding?
A. Warranty work
B.Rework
C.Testing
D. Scrap

公司董事担心项目失败,并聘用一名项目经理,以确定应分配额外的资金确保项目成功。项目经理应建议对哪项活动分配额外资金?
A.保修工作
B.返工
C.测试
D.废料

答案:C
解析:本题点在于质量成本。预防胜于检查,测试属于质量成本中的一致性成本,其它三项都属于非一致性成本。