PMP:每日一题-40

2019.9.3每日一题:

A project team meeting is scheduled in direct conflict with a senior manager’s team-building exercise. All project team members are required to attend both. What should the project manager do to accommodate the senior manager?
A. Attend the team-building exercise with the orient team.
B. Reschedule the project team meeting.
C. Suggest that the team-building exercise be rescheduled.
D. Conduct the team meeting and then attend the team-building exercise.

一次项目团队会议的安排时间与高级经理的团队建设训练直接发生了冲突。所有项目团队成员都必须参加这两项活动。为了适应高级经理,项目经理应该怎么做?
A.与项目团队一起参加团队建设练习。
B.重新安排项目团队会议的时间。
C.建议重新安排团队建设练习的时间。
D.召开团队会议,然后参加团队建设练习。

答案:B
解析:本题点在于冲突处理,B参考答案为回避,是避免冲突的较好解决措施。